14 CFR § 25.1310

Power source capacity and distribution.

← Previous SectionNext Section →
Read in Subpart F
Part 25 Contents
  • Special Federal Aviation Regulation No. 13
  • Special Federal Aviation Regulation No. 109
  • Subpart A: General
  • Subpart B: Flight
  • Subpart C: Structure
  • Subpart D: Design and Construction
  • Subpart E: Powerplant
  • Subpart F: Equipment
  • Subpart G: Operating Limitations and Information
  • Subpart H: Electrical Wiring Interconnection Systems (EWIS)
  • Subpart I: Special Federal Aviation Regulations
  • Appendix A to Part 25
  • Appendix B to Part 25
  • Appendix C to Part 25
  • Appendix D to Part 25
  • Appendix E to Part 25
  • Appendix F to Part 25
  • Appendix H to Part 25: Instructions for Continued Airworthiness
  • Appendix I to Part 25: Installation of an Automatic Takeoff Thrust Control System (ATTCS)
  • Appendix J to Part 25: Emergency Evacuation
  • Appendix K to Part 25: Extended Operations (ETOPS)
  • Appendix L to Part 25: HIRF Environments and Equipment HIRF Test Levels
  • Appendix M to Part 25: Fuel Tank System Flammability Reduction Means
  • Appendix N to Part 25: Fuel Tank Flammability Exposure and Reliability Analysis
  • Appendix O to Part 25: Supercooled Large Drop Icing Conditions
(a)

Each installation whose functioning is required for type certification or under operating rules and that requires a power supply is an “essential load” on the power supply. The power sources and the system must be able to supply the following power loads in probable operating combinations and for probable durations:

(1)

Loads connected to the system with the system functioning normally.

(2)

Essential loads, after failure of any one prime mover, power converter, or energy storage device.

(3)

Essential loads after failure of—

(i)

Any one engine on two-engine airplanes; and

(ii)

Any two engines on airplanes with three or more engines.

(4)

Essential loads for which an alternate source of power is required, after any failure or malfunction in any one power supply system, distribution system, or other utilization system.

(b)

In determining compliance with paragraphs (a)(2) and (3) of this section, the power loads may be assumed to be reduced under a monitoring procedure consistent with safety in the kinds of operation authorized. Loads not required in controlled flight need not be considered for the two-engine-inoperative condition on airplanes with three or more engines.