JO 7110.65 — Air Traffic Control
JO 7110.65 5-9-8
SIMULTANEOUS INDEPENDENT CLOSE PARALLEL APPROACHES –PRECISION RUNWAY MONITOR (PRM) APPROACHES
This reproduces published FAA reference text for study. It does not replace the current official FAA publication or regulation.
TERMINAL
When conducting PRM approaches, apply all pertinent provisions of paragraph 5-9-7 and the following:
PRM approaches may only be conducted when charted in the approach title, and where instrument approach charts specifically authorize simultaneous approaches. REFERENCE-
P/CG - Precision Runway Monitor (PRM) System.
P/CG - Simultaneous Close Parallel Approaches.
P/CG - PRM Approach.
PRM approaches must be assigned when conducting instrument approaches to dual and triple parallel runways with runway centerlines separated by less than 4,300 feet.